Subcontract held to govern works commenced before execution
Clare Mendelle and James Goldthorpe examine a case which considered which terms governed liability for works carried out prior to the execution of a contract.
- Details
Balfour Beatty Regional Construction Limited v Van Elle Limited [2021] EWHC 794 (TCC)
Case Background
Balfour Beatty, the main contractor on a sub-sea cable manufacturing facility in Newcastle, engaged Van Elle as sub-contractor to perform piling works. One section of these works was largely completed by Van Elle after Balfour Beatty had accepted Van Elle’s quotation and issued a letter of intent, but before the parties entered into a subcontract. After the works were completed, defects were discovered which required Balfour Beatty to carry out remediation works.
Balfour Beatty claimed damages for breach of contract against Van Elle but Van Elle argued that the completed works were not covered by the executed subcontract. Instead, they alleged that the works were governed by a contract that was formed when its earlier written quotation was accepted by Balfour Beatty by its conduct. This alleged contract (unlike the subcontract) incorporated Van Elle’s standard terms and conditions, which Van Elle considered significantly limited its liability for losses.
The court had to decide whether the works were governed by the executed subcontract, or by Van Elle’s standard terms and conditions.
Decision and Reasoning
The judge found in favour of Balfour Beatty and held that the subcontract had governed all the works, including those carried out prior to execution.
Having assessed the contemporaneous documentary evidence, he concluded that the parties had intended for there to be only one contract. Crucially, Van Elle had requested a letter of intent on several occasions and was not content to proceed with the works based on the quotation which they later argued formed the basis of a contract. The requested letter of intent included the early works; therefore, the subcontract also included those works.
Commentary
While not a surprising decision, it is helpful for employers who need to commence works under a letter of intent before a contract is finalised as the courts are likely to find that any interim contract is superseded by a subsequent formal contract.
Both employers and contractors should also take note of the judge’s obiter remarks on the efficacy of Van Elle’s standard terms and conditions limiting liability, which he suggested may be a lot less effective than they might hope them to be.
Clare Mendelle is a professional support lawyer and James Goldthorpe a paralegal at Sharpe Pritchard LLP
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email enquiries@sharpepritchard.co.uk
Click here to view our archived articles or search below.
|
OUR RECENT ARTICLES
Jul 03, 2025
IPA guidance 2025: Managing PFI distress and preparing for expiryAanya Gujral and David Owens dive into the recent guidance published on managing the risks associated with Private Finance Initiative (“PFI”) projects.
Jul 03, 2025
Data (Use and Access) Act – Updating Data Protection Law and moreOn the 19th June 2025, the Data Use and Access Bill (“DUA Bill”) received Royal Assent to become the Data Use and Access Act 2025 (“DUA Act”).
Jun 24, 2025
Getting new PPP right: Smarter tools for smarter infrastructureNicola Sumner, Steve Gummer and Roseanne Serrelli discuss the 'dos and don'ts' of Public-private Partnerships in their new form.
Jun 19, 2025
Zones/RABs and heat networks: The path to an investible infrastructure asset class?The UK’s new heat network zoning framework (the outlines for which were drawn by the Energy Act 2023) is set to redefine how low‑carbon heating is delivered by creating geographic zones, where district heat networks are the mandated, optimal solution.
Jun 17, 2025
Partial debt guarantees- Reviving Investment in UK Water InfrastructureIs it Time for a Public Sector Major Infrastructure Debt Guarantor?
Jun 10, 2025
Court gives clarity on consultations : R (The National Council for Civil Liberties) and others v The Secretary of State for the Home DepartmentChloe Woodward and Joe Walker discuss a recent judgment on when engagement with third parties constitute a formal consultation and must therefore adhere to case law on being 'run fairly'.
|
ABOUT SHARPE PRITCHARD We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here. |
OUR NEXT EVENT
|
OTHER UPCOMING EVENTS
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |