Are Collateral Warranties Construction Contracts? Timing is Key.
Clare Mendelle and Anna Sidebottom examine the recently decided case of Toppan v Simply[1], which has provided guidance on when collateral warranties may be considered “construction contracts” under the Housing Grants, Construction and Regeneration Act 1996 and so give the warranty holder the right to adjudicate.
- Details
Simply was engaged in 2015 under a JCT Design and Build Contract to construct a care home owned by Toppan and operated by Abbey. Under the terms of the building contract, Simply was obliged to provide a collateral warranty for the benefit of Abbey (the Abbey Collateral Warranty).
Practical completion occurred in October 2016. Simply was subsequently notified of fire safety defects in January 2019 and remedial works to correct these were completed in February 2020.
Simply provided the Abbey Collateral Warranty in October 2020, under which Simply warranted that:
It had “performed and would continue to perform diligently its obligations under the [Building] Contract”; and
In carrying out and completing the works, it had “exercised and will continue to exercise all the reasonable skill and care…”.
Abbey and Toppan started separate adjudications against Simply and were both awarded substantial sums of money. When Simply did not comply with the decisions, Toppan and Abby applied for summary judgment enforcement.
The TCC’s Decision
The judge found that the Abbey Collateral Warranty was not a construction contract for the purposes of the Act and that there was, therefore, no right to adjudicate the dispute.
In reaching this decision the judge considered the principles laid down in a 2013 case Parkwood Leisure Ltd v Laing O’Rourke Wales and West Ltd[2] (which had found that the parties’ collateral warranty was in fact a construction contract), and then construed the wording of the Abbey Collateral Warranty against the relevant factual background.
Whilst noting that the Abbey Collateral Warranty referred to both a past state of affairs (“has performed” / “has exercised”) and future performance (“will continue to perform” / “will continue to exercise”), he considered that it could not be construed as a construction contract within the meaning of the Act because the agreement between Abbey and Simply was not an agreement for “the carrying out of construction operations”. Key to this decision was the timing of the execution: the Abbey Collateral Warranty was executed 4 years after practical completion and 8 months after remedial works had been completed.
As points of principle, he considered:
– Where a contractor agrees to carry out uncompleted works in the future, that will be a very strong pointer that the collateral warranty is a construction contract, and the parties will have a right to adjudicate.
– Where the works have already been completed and even latent defects have been remedied, a construction contract is unlikely to arise and there will be no right to adjudicate.
Even though Parliament intended Section 104 of the Act to be construed widely, applying ‘commercial common sense’ to the facts the judge couldn’t see how a “collateral warranty executed four years after practical completion and months after the dispute remedial works had been remedied…can be construed as an agreement for carrying out of construction operations”.
In effect, by the time the Abbey Collateral Warranty was executed it was a warranty of a state of affairs past or future, akin to a manufacturer’s product warranty. Accordingly, it was held that it was not a construction contract for the purposes of the Act and so there was no contractual right to adjudicate.
Comment
Beneficiaries of collateral warranties who want to benefit from the right to adjudicate will need to consider the timing of execution in addition to the wording of the warranty; getting the warranty executed before the works are completed will increase the chances of it being considered a construction contract.
Sharpe Pritchard has extensive experience preparing all forms of construction contracts and ancillary agreements. If you require further information or advice, please contact Justin Mendelle.
Clare Mendelle is a professional support lawyer and Anna Sidebottom a Trainee Solicitor at Sharpe Pritchard LLP
[1] Toppan Holdings Ltd and another v Simply Construct (UK) LLP [2021] EWHC 2110 (TCC)
[2] Parkwood Leisure Ltd v Laing O’Rourke Wales and West Ltd [2013] EWHC 2665 (TCC)
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email enquiries@sharpepritchard.co.uk.
Click here to view our archived articles or search below.
|
OUR RECENT ARTICLES
Jul 03, 2025
IPA guidance 2025: Managing PFI distress and preparing for expiryAanya Gujral and David Owens dive into the recent guidance published on managing the risks associated with Private Finance Initiative (“PFI”) projects.
Jul 03, 2025
Data (Use and Access) Act – Updating Data Protection Law and moreOn the 19th June 2025, the Data Use and Access Bill (“DUA Bill”) received Royal Assent to become the Data Use and Access Act 2025 (“DUA Act”).
Jun 24, 2025
Modifying subsidies: What is permitted and what is not?Beatrice Wood and Oliver Slater explore recent developments and discuss the process of awarding subsidies.
Jun 24, 2025
Getting new PPP right: Smarter tools for smarter infrastructureNicola Sumner, Steve Gummer and Roseanne Serrelli discuss the 'dos and don'ts' of Public-private Partnerships in their new form.
Jun 19, 2025
Zones/RABs and heat networks: The path to an investible infrastructure asset class?The UK’s new heat network zoning framework (the outlines for which were drawn by the Energy Act 2023) is set to redefine how low‑carbon heating is delivered by creating geographic zones, where district heat networks are the mandated, optimal solution.
Jun 17, 2025
Partial debt guarantees- Reviving Investment in UK Water InfrastructureIs it Time for a Public Sector Major Infrastructure Debt Guarantor?
|
ABOUT SHARPE PRITCHARD We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here. |
OUR NEXT EVENT
|
OTHER UPCOMING EVENTS
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |